Full-Cycle Project Case: Hall 2 (Building B), Chengdu Kechuang Eco-Island Intelligent System Project | Sichuan DCH Technology Co., Ltd.
CASE STUDY · ENTERPRISE CAMPUS INTEGRATION

Full-Cycle Project Case: Hall 2 (Building B), Chengdu Kechuang Eco-Island Intelligent System Project | Sichuan DCH Technology Co., Ltd.

Published: Aug 25, 2026  · Category: Enterprise Campus Integration  · Department: Project Management Office  · 1 reads

2号馆(B栋)楼体外景(现场实拍)
Fig. 1 | Exterior view of Hall 2 (Building B) (on-site photo)
2号馆(B栋)楼内景观(现场实拍)
Fig. 2 | Interior landscape of the Eco-Island (on-site photo)

1. Project Background

The Chengdu Kechuang Eco-Island (formerly "Unicorn Island") Pilot Base project is located in Tianfu New Area, Chengdu, serving as the city's key platform for scientific and technological achievement transformation. Hall 2 (Building B) is part of the base; the project owner (tenderer) is Chengdu Tiantou Luxi Zhigu Park Construction Co., Ltd., and the general contractor is the consortium of Chengdu Jiangong Decoration Engineering Co., Ltd. (lead) and China Southwest Architectural Design and Research Institute. The general contracting scope follows the design-build tender announcement (National Public Resources Trading Platform, Sichuan, Aug 12, 2025), with the bid evaluation result officially published on Sep 9, 2025.

As the intelligent system subcontractor (cost-controlled mode), Sichuan DCH Technology Co., Ltd. undertakes the construction and integration of intelligent systems within Hall 2 (Building B), covering approx. 12,121 m² across parts of floors 3F–4F, -1F, 2F and 6F. Works started on Nov 19, 2025 and were completed on Apr 8, 2026, an actual duration of about 140 days.

Compliance note: The intelligent subcontract task was registered on Chengjian E-Cai (the bidding platform of Chengdu Jiangong Decoration Engineering Co., Ltd.), project No. HS-ZBRW-2025-014213 (see official source ② below).

2. Project Timeline

DateMilestoneNote
2025年8月12日Tender announcementOfficialChengdu Tiantou Luxi Zhigu
2025年9月9日Bid evaluation resultOfficialJiangong Decoration + SW Architectural
2025年11月17日Subcontract task registrationOfficialChengjian E-Cai, No. HS-ZBRW-2025-014213
2025年11月19日Site mobilizationDCHMobilization, drawing review, safety briefing
2026年1月Process change instructionOwnerScheme and sequence adjusted; schedule extended
2026年4月8日Subcontract completionDCHScope completed and accepted
2026年4月16日HandoverOperatorOperator signed; formal delivery

3. Key Implementation Points

1. Overall Scope (from the official tender)

Source: National Public Resources Trading Platform (Sichuan), design-build tender announcement for Hall 2 (Building B) ancillary works (Aug 12, 2025); tenderer: Chengdu Tiantou Luxi Zhigu Park Construction Co., Ltd.
  • Scope: parts of floors 3F–4F, -1F, 2F and 6F (public corridors, shared areas, elevator lobbies), independent support rooms, and B-building basement spaces
  • Floor area: approx. 12,121 m²
  • Function: composite business space for HQ support, R&D innovation and professional services
  • Planned general contracting duration: ~90 calendar days (start Sep 17, 2025; completion Dec 15, 2025; defect liability 24 months)

2. DCH Subcontract Scope

Sichuan DCH Technology Co., Ltd. undertakes the intelligent system subcontract (cost-controlled mode) under the "M&E works" item of the general contracting scope.
  • Information Technology Systems (ITS): structured cabling, wired & wireless networks
  • Building Management System (BMS): BA system, intelligent control, energy monitoring
  • Public Security Systems (PSS): CCTV, access control, swing gates
  • System commissioning and overall handover support

3. Key System Delivery

ITS: planning and deployment of structured cabling and wired/wireless networks, with information points uniformly planned by floor and function to avoid disorderly later cabling.

BMS: building automation (BA), intelligent control and energy monitoring. Honeywell™ DDC controllers provide centralized monitoring of M&E equipment with synchronized energy data collection.

PSS: CCTV, access control and passage gates. Access control panels manage entrances and visitor passage, with all circuits labeled for easy maintenance.

4. Outcomes & Value

  1. On-time delivery: ~140 days from mobilization to handover, all subcontract works completed as planned
  2. Signed acceptance: the operator signed the handover confirmation on site, formally closing the project
  3. Serial deployment: accumulated experience is reusable for subsequent intelligent projects in the same park
CASE · WIN-WIN

Similar needs? Let us discuss your project

Leveraging 100+ implementation experiences for one-on-one solution design.

100+Delivered Cases20+Industry Scenarios10+Partners

Knowledge Base AI Assistant

Hello, I am the Dachanghui Knowledge Base AI Assistant. Ask me anything about products, solutions or integration, and I will answer based on knowledge base materials.
What does intelligent system integration include? What can weak-current engineering do? How to contact after-sales O&M?
EN